Pooley Bridge Gets Its Bridge Back

Civil Earth Structures Geotechnical Structural Temporary Works

On December the 6th 2015, during storm Desmond, substantial flooding in Cumbria resulted in the loss of the masonry arch bridge within the village of Pooley Bridge. The original bridge was erected in 1764 (itself replacing an earlier bridge from the 16th century) and was positioned at the outlet of…

Dukinfield Waste Water Treatment Works – Nitrifying Trickling Filter

Civil Geotechnical Structural

PaSCoE were commissioned to design the civils structures associated with the construction of a new Nitrifying Trickling Filter (NTF) to supplement an existing bank of NTF’s supplied by a single distribution chamber. The works included the design and detailing of piled foundations for the new post tensioned precast segmental tank…

Ben Gill, Cumbria – Back to Nature

Civil Earth Structures Geotechnical Structural

Engineering work on the weir of Ennerdale Water in the 1950s raised the level of the lake, increasing its storage capacity and ensuring a more secure potable water supply. As part of this work, one of the tributaries of the River Ehen (Ben Gill) was diverted to Ennerdale Water via…

14m high wall supports the flow of electricity from Scotland to England

Civil Earth Structures Geotechnical Structural

As part of the major FACTS (Flexible Alternating Current Transmission System) project by National Grid to boost the flow of electricity from Scotland to England cutting edge design TCSC (thyristor controlled series compensation) equipment was required at the Hutton 400 kV Hutton Substation near Kendal in Cumbria. This exciting project…

Preston WTS

Geotechnical

The Lancashire Waste Network comprises the treatment of household waste from the 15 local authorities at 4 Central Waste Treatment Facilities supported by 11 Waste Transfer Stations. The Preston Waste Transfer Station (WTS) will process 60,000 tonnes per annum of mixed waste with future expansion to include a 26,000 tonnes…

Midland Quarry

Earth Structures Geotechnical

A former sandstone and diorite quarry on a 16hectare site near Nuneaton was to be redeveloped by Redrow Homes for new residential housing. To maximise the available land required the construction of a new retaining structure within the existing quarry. The existing quarry comprised a partially flooded Main Void and…