At Rhiwbina Station there was a requirement to encapsulate the existing footbridge bridge and staircase to carry out repairs and blast and paint.
Due to limited gauge clearance it was not possible to undersling a traditional scaffold to provide access.
PaSCoE developed an innovative scaffold design solution that included a scaffold deck to span the single track which can be lowered during possessions & raised during operational periods.
This removed the need to repeatedly construct, encapsulate, and remove the scaffold deck during each possession.